300 Tesla Semis, 25 Charging Bays: Oakland's New Truck Depot
The Port of Oakland opened its first public charging depot for electric big rigs on Monday, November 23, and rolled out the first of the Tesla Semis that WattEV plans to run on a freight corridor out of the Bay Area. The site at 8407 Edgewater Drive can charge 25 medium- and heavy-duty trucks at once at up to 240 kW each, or seven trucks at 1.2 MW, according to the Port of Oakland's announcement and TeslaNorth's report.
The bigger number sits behind the chargers. The port says 300 Tesla Semis will serve Oakland, with the first batch due before the end of this year and the rest arriving in 2027. That fleet is the Northern California share of the 370-truck order WattEV announced in May, and it is the clearest sign yet of the Semi moving from pilot fleets into port drayage at scale.
At a glance
- What opened: Northern California's first public heavy-duty electric truck charging depot, per the port.
- Capacity: 25 trucks at up to 240 kW each, or seven at 1.2 MW.
- Fleet: 300 Tesla Semis planned for the port (TeslaNorth reports WattEV's figure as more than 300). First batch before year-end, balance in 2027.
- Route: a corridor from the Bay Area to Sacramento, the Central Valley and Nevada.
- Open to others: TeslaNorth reports the depot is open to other electric truck fleets, not only WattEV's Semis.
- Not disclosed: how many Semis debuted at the opening.
How Oakland got here
| Date | Milestone | Source |
|---|---|---|
| 2024 | The Bay Area Air District awards a $5 million Community Air Protection grant for the depot. | Bay Area Air District |
| June 24, 2025 | WattEV breaks ground at 8407 Edgewater Drive, calling it its sixth heavy-duty depot in California. The plan at the time: 25 trucks at up to 240 kW or six at 1.2 MW. | WattEV release |
| April 2026 | The Air District says it helped WattEV secure a separate $4.1 million loan for the Oakland project. | Bay Area Air District |
| May 5, 2026 | WattEV orders 370 Tesla Semis, with more than 300 for a joint program with the Port of Oakland. First 50 deliveries to begin in 2026, full fleet by the end of 2027. | Electrek, FreightWaves |
| November 23, 2026 | The depot opens and the first Semis for the corridor debut. The port says the first batch is due before year-end. | Port of Oakland, TeslaNorth |
Who is claiming what
| Claim | Who says it | Our read |
|---|---|---|
| 300 Tesla Semis will serve the port | Port of Oakland | TeslaNorth reports WattEV's number as more than 300. Both trace back to the May order for 370 trucks statewide. |
| Electric rigs cost half as much to operate as comparable diesels | WattEV, quoted in the port's announcement | WattEV ties this to current high diesel prices. TeslaNorth describes WattEV's comparison as energy cost per mile, not the full cost of owning and running a truck. |
| Seven trucks can charge at 1.2 MW | Port of Oakland, TeslaNorth | The 2025 groundbreaking release said six. Opening-day materials say seven. |
| Charging dwell times of 30 minutes or less | Port of Oakland | A design target for megawatt charging, framed as comparable to diesel refueling. |
| WattEV's eighth heavy-duty depot in California | TeslaNorth | WattEV called Oakland its sixth at groundbreaking and has opened other sites since, including Fresno. |
WattEV co-founder and CEO Salim Youssefzadeh pitched the opening as an ecosystem that will "blow away traditional diesel freight hauling", in remarks released by the port. He also noted that most truck charging so far has been concentrated in Southern California, which is why a depot at Oakland's seaport matters for routes north and east.
The chargers are built. The question now is how fast 300 trucks actually show up.
What we could not confirm
- How many Semis debuted Monday. TeslaNorth says WattEV did not give a number.
- Whose megawatt hardware is installed. WattEV's May announcement said the Oakland and Fresno sites would use Tesla's Megawatt Charging System. The opening-day materials we read describe megawatt charging without naming the supplier.
- The delivery schedule beyond "first batch before year-end." No monthly or quarterly targets were published.
- Charging prices for outside fleets. The depot is described as public, but no rates were announced.
What it means if you drive a Tesla
Nothing changes for your Model 3, Model Y or Cybertruck charging. Every announcement describes this as a depot for medium- and heavy-duty trucks, so plan your Bay Area stops around Superchargers as usual. Where it matters is the bigger picture: Semi deliveries are picking up across the country, and TeslaNorth reported last week that HMD Trucking took delivery of 50 Semis in Illinois. Oakland is the first big test of the Semi on a public port depot in Northern California, and the numbers WattEV reports over the next year will say more about the truck than any launch event.
For reporters and researchers
This page summarizes public statements from the Port of Oakland, WattEV, the Bay Area Air District and news outlets as of November 23, 2026, and flags where they differ. Suggested citation: EV Bandit, "300 Tesla Semis, 25 Charging Bays: Oakland's New Truck Depot," November 23, 2026.
Related on EV Bandit
- Tesla Unveils Powercore: A 7.4 MW Transformer, Inverter and Breaker in One Box
- 773 Cybercabs and a Second City: Tesla's Texas Robotaxi Timeline
Sources
- Port of Oakland announcement, via Newsroom America
- TeslaNorth: Tesla Semis debut at WattEV's Port of Oakland depot
- Bay Area Air District: WattEV loan and grant
- WattEV: Port of Oakland groundbreaking (June 2025)
- Electrek: WattEV orders 370 Tesla Semis
- FreightWaves: WattEV orders 370 Tesla Semis
- TeslaNorth: HMD Trucking takes delivery of 50 Semis
Spotted a Semi on I-880 yet? Share it with the Tesla Model Y Owners group on Facebook, 170,000 members strong.